Timeline

Design it

Build it

Launch it

Design it • Build it • Launch it •

Schedule Overview

Team Hōkūlele is on track, as the majority of the tasks planned for completion have been completed. However, the team did not receive UROP funding like it had hoped. Because of this, the fundraising to reach the target will be more difficult than originally anticipated. The team will focus on securing other funding opportunities in order to compensate for this. The team expects to remain on schedule, and the next milestone will be purchasing materials to ensure they arrive in time to begin the fabrication process.

Completed Milestones

Proposal

The team presented and submitted the Request for Proposal Report on September 25, 2024. This report introduced the project mission statement and a proposed design, including descriptions and inspirations. It also included the Gantt chart and a preliminary work breakdown structure. Additionally, the report introduced the team members, outlined team policies and expectations, and established the foundation for the team's dynamics.

Preliminary Design Review

The Preliminary Design Review was submitted on November 4, 2024. This report included the decision-making matrices (DMMs) and the resulting designs. It also outlined the current testing plans, as well as the risk analysis and mitigations identified by the team.

In-Progess Milestones

Critical Design Review

The Critical Design Review is going to be submitted on December 9, 2024. This report will showcase the finalized designs for the rocket's components using CAD models and assemblies. It will also detail the current cost breakdowns for each subsystem and the finalized testing plan. Additionally, the report will introduce the FMECA and Fault Tree, which explains subsystem-level failures and outlines strategies to reduce their occurrence.

Fundraising

In terms of fundraising during the Fall 2024 semester, the team applied for grants through the Hawaiian Airlines Kōkua Giving Program and is currently applying for the Associated Students of the University of Hawaiʻi (ASUH) Research Award. The team is also conducting a Samurai Snack Pack fundraiser, with additional fundraisers planned for Spring 2025.

Finalizing Designs

The team is currently finalizing and updating designs to align with the 2025 FAR-Unlimited Rules and Regulations.

Purchasing Materials

The team is preparing a purchase order for approval to ensure the items are available by the start of the spring semester.

Future Milestones

Assembly

In the future, the team will continue assembling the rocket and its subsystem components.

Testing

The team will conduct testing throughout the rest of the spring semester to ensure the rocket is ready for the competition in early June.

Competition

The end goal is to compete in the FAR-Unlimited Competition in the summer of 2025. The team will ensure the rocket is fully assembled and tested to perform at its best during the competition.

Fall 2024-2025 Administration Gantt Chart

Fall 2024-2025 Structure Gantt Chart

Fall 2024-2025 Propulsion Gantt Chart

Fall 2024-2025 Recovery & Avionics Gantt Chart

Fall 2024-2025 Payload Gantt Chart

Fall 2024-2025 Communications & Ground Station Gantt Chart